Three Gorges Dam Hydroelectric Power Plant, China

(February 1, 2010) Overview of the Three Gorges Dam Project.

Three Gorges Dam Project (TGP) is the world’s largest hydropower complex project located in one of the three gorges of the Yangtze River, Xilingxia gorge in Hubei province, China. The gorge controls about 1 million km² of drainage area and averages a runoff of 451 billion m³ annually. China Three Gorges Corporation (CTGPC) acts as the legal entity for TGP. CTGPC is responsible for the construction, operation and financing of the project.

Construction on the Three Gorges Dam was completed in 2008. The dam stands 185m high and 2,309m wide making it the world’s largest hydro plant in the world, well ahead of Brazil’s 12,600MW Itaipu installation.

A total of 32 main power generators are planned, of which 12 sets on the right bank and 14 sets on the left were installed in 2006 and 2008 respectively. They were operational in October 2008 and generated a total of 18,300MW. Another six generators are being installed underground to make a total of 32 power generating sets, which are expected to become fully operational in 2011. These six were added to the project in 2002. Upon completion of the installation of the additional generators, the plant will produce 22,500MW of electricity.

In September 2009, the project proved its power generation benefits by generating 348.4TWh of electricity which is about one third of the project cost. It is expected to generate 150,000GWh excess power than the initially planned 224,400GWh for a total of 370,000GWh by the end of 2009.

Three Gorges project

The Three Gorges Dam project involves harnessing the Yangtze River, Asia’s longest, to generate prodigious amounts of electricity. Output should be 85TWh/y, close to one tenth of current Chinese requirements. The dam also checks disastrous floods downstream, which have claimed hundreds of thousands of lives this century alone. Improved navigability on the river should also allows much larger ships to sail from Shanghai as far as Chongqing, upstream from the dam and 2,000km from the sea, to aid China’s burgeoning domestic and export trade.

The project is located 44km from the city of Yichang in Hubei province. This point is at the end of a series of steep canyons which will form a 630km reservoir, with an average width of 1.3km. Its capacity is 39.3 billion m³.

The plant is the centre of a broad plan for central China’s electricity industry. Related transmission and distribution installations will be linked to the three regional grids taking Three Gorges power, forming a single system from the coast to the border of Tibet.

The grids and their planned shares of offtake are: Central China Power Network (55%); East China Power Network (39%); Sichuan Provincial Grid (6%).

The project consists of a concrete gravity dam with a spillway in the middle. The power house and non-overflow section are stationed at both ends of the dam. The length of the dam is 2309.47m and the storage level is 175m.

The project has 34 generators, of which 32 are the main generators. The other two are power generators with a capacity of 50MW each.

The plant took 17 years for construction and was built in stages by state-backed sponsor China Yangtze Three Gorges Dam Project Development Corporation. Initial works began in 1993. Up to the end of 1996, around $2.3bn was invested. Main equipment orders for the 9,800MW first phase were placed in 1997. 14 of 32 Francis units of 700MW each were brought on-line on the left bank of the river (between 2003 and 2006).

In the second phase, 12 more 700MW units were added on the opposite bank, taking the total to 18,200MW.

During the second phase, the dam was built to a height of 87m, and 14 turbines and a 135m-high permanent ship-lock was built on the southern bank. In the final phase, the dam was raised to a maximum height of 185m and an additional 12 turbines were installed on the northern bank of the Yangtze River.

As of May 2010, spiral casing installation was completed for the generating unit 27. With this, the spiral casing of all the six underground generating units was completed. The spiral casing began on 26 May 2009.

Plant

On 18 October 2006, the first 14 generators became fully operational, generating 9,800MW at water level of 156m.

The first (No.22) of the 12 generators became operational on 11 June 2007 and the final generator (No.15) was brought into operation on 30 October 2008.

On 30 June 2009, all the 24 generators and two power generators were switched on. They produced 16,100MW of power, less than the maximum capacity of 18,300MW. The plant reached its full capacity in August 2009 due to elevated upstream water level and river flow during the floods for a short duration.

Ecological concerns

The long-term ecological effect of the dam has been described as possibly catastrophic. The dam will disrupt heavy silt flows in the river. It could cause rapid silt build-up in the reservoir, creating an imbalance upstream, and depriving agricultural land and fish downstream of essential nutrients. Since these problems would also hit the plant’s turbines and millions of farmers and fishermen, considering ecology is common sense.

Environmentalist and political opposition to the Three Gorges Dam has been intense. The most emotive issue was the forced relocation of 1.27 million people in September 2009. China points to detailed plans to actually improve the lives of those affected, but residents complained of the resettlement funds and job retraining promises being denied.The farmland, which will be flooded is more fertile than higher ground, and some 1,600 factories will be submerged.

Opponents of the Three Gorges Dam have had more success outside China. The World Bank, stung by vicious critiques of other hydro projects it sponsored, decided not to fund the project. The US Export-Import Bank also bowed to pressure. The bank hoped to gain further environmental information from the Chinese that would allow a positive decision – it is not against the project in principle. Moreover, its stance did not prevent US groups from bidding for contracts, nor US commercial banks from financing their operations.

Support for the project

European governments, however, have snubbed Three Gorges opponents. The export credit agencies of Germany, Switzerland, Sweden, France and the UK all promised support for potential suppliers from their countries.

Japan, after initial hesitation, followed their lead. Canada also offered financing to its companies. Long-term commercial loans by banks in these countries backed up the credits.

Arguments marshalled by the Japanese to support their final decision do provide some answers to the project’s critics.

After intensive reviews by the Japanese Ministry of International Trade and Industry, Japan claimed the project offered the following main benefits:

Flood control: Japan believes the project will achieve its objectives in this area, despite claims that it could actually increase the risk of floods, either through changes in silt flow or a catastrophic dam collapse. This issue in particular has attracted popular sympathy for the project in Japan.

Emissions reduction: the plant’s output will be equivalent to several large coal-fired plants burning 40 to 50 million t/y. If it is not built, soaring Chinese emissions will rise even faster, causing more acid rain in Japan

.

Relocation: Japan believes current plans are adequate, although the situation would need to be kept under review.

China initially insisted that potential problems had been identified and dealt with. However, there have been further recent calls on Western governments and companies to refrain from further supporting the project until resettlement and human rights problems are resolved. There have been claims that the dam does not address the real source of flooding (deforestation in the Yangtze watershed and the loss of lakes that alleviated floods because of siltation, reclamation and uncontrolled development).

Corruption scandals have also plagued the project. Contractors allegedly won bids through bribery and then siphoned off construction funds by skimping on equipment and materials. After a number of accidents, much of the project’s infrastructure ripped out in 1999.

Project finance and contracts

The official total cost figure was estimated as 203 billion Yuan (元) ($29bn), met primarily by special taxes on electricity consumption and revenue from the first phase units operating. But the cost was decreased to 180bn due to lower inflation rate during construction.

The Three Gorges Dam main equipment order was divided between six top foreign groups, drawn into two project alliances. Out of 14 700MW units, eight were assigned to Alstom, ABB and Kvaerner, and six to Voith, Siemens and GE.

Alstom had not joined the partnership between ABB and Kvaerner for the bid, or any other leading global name, but the Chinese side clearly preferred to diversify its risks and gain broad access to Western technology rather than rely extensively on one supplier. This probably helped the Voith, Siemens and GE Hydro alliance, which was formed well ahead of bidding, and represents an unusually strong concentration of expertise (GE does not normally work with arch-rival Siemens).

Within the two groupings, work was further divided as follows:

For the eight units, Alstom was the prime turbine contractor, with work worth $212m. Several of its units were involved, lead by Mecanica Pesada of Brazil and the Tianjin Chinese hydro turbine joint venture. Kvaerner of Norway supplied design, technology, five runners and components. It put its share of the business at $40m. ABB was chosen to supply eight generators (ABB does not make hydro turbines) under a contract it said was worth around $250m. This took the total value of the eight-unit order to around $500m.

The six-unit order was split between Voith, the lead turbine contractor, Siemens, which was to supply generators (like ABB, it does not make hydro turbines), and GE, which has to carry out both turbine and generator work. The entire order is worth an estimated $350m.

Since the first turbine and generator contracts were signed in 1997, Alstom has acquired ABB’s power division, and GE Hydro has acquired Kvaerner. In March 2004, Alstom was awarded a €163m contract to supply the four 700MW turbines and associated generators to the project’s Right Bank powerhouse.

Technology transfer

Two Chinese equipment suppliers played a major role in the later stages of the first phase. Harbin Power Equipment and Dongfang Electrical Machinery worked with the two foreign groupings, benefiting from extensive technology transfer requirements. Harbin co-operated with the Alstom, ABB and Kvaerner grouping, and Dongfang with the Voith General Electric and Siemens consortium along with Chinese company Oriental Motor. The last two units of the first phase were almost entirely constructed in China.

Distribution

The TGP power distribution and transmission infrastructure was completed in December 2007 at a cost of about 元34.3bn. Power generated from the dam is transferred to two cities including Shanghai and nine provinces from three directions. A 500kV DC transmission line on East China Grid which has a capacity of 7,200MW, a 500kV DC transmission line (HVDC Three Gorges-Guangdong) to the South China Grid having 3,000MW capacity and a 500kV AC transmission line to the Central China Grid having 12,000MW capacity support the distribution.

The East China Grid is connected to three 500kV DC transmission lines which include HVDC Three Gorges-Changzhou with a capacity 3,000MW, HVDC Three Gorges-Shanghai with a capacity 3,000MW and HVDC Gezhouba-Shanghai with a capacity 1,200MW.

Construction

Construction tasks were assigned to Chinese groups. Shortly before the equipment announcements, contracts worth $800m went to Gezhouba Share Holding Ltd, Yichang Qingyun Hydropower Joint Management Co and Yichang Three Gorges Project Construction 378 Joint Management. The work included the construction of dikes and the powerhouse.

The plant construction involved excavation of 102.83 million m³ of rock and earth and refill of 31.98 million m³, 27.94 million m³ of concrete placement and installation of 256,500t metal frame.

Power-technology.com

Read the original article here