San Ignacio, Belize — When a Canadian power company proposed a dam along a branch of the nearby Macal River, officials here welcomed the investment. They hoped the project would wean Belize from electricity bought from Mexico, and provide a new water source for an existing dam and power plant that struggle during the dry season.
But the plan has unleashed a barrage of criticism from environmentalists, who have also decided to look beyond Belize’s borders for support, taking their cues from the flows of global capital.
If local developers and government officials are wooing foreign investors with environmentally sensitive projects, they say, then environmental activists must respond by bringing in help from abroad.
The environmental groups fear the project would flood a sensitive jungle habitat whose thick riverbank vegetation offers a bountiful green feast for tapirs — Belize’s noodle-nosed national animal — which share the remote area with jaguars and scarlet macaws.
They have also questioned the dam as unnecessary and uneconomical, and say it will enrich only a small clique while not cutting electricity rates for residents.
But their campaign was kicked up a notch when they brought in the Natural Resources Defense Council, an international group that has placed the Macal River on a list of 12 “biogems” — environmentally important areas threatened by development.
The support of international groups has emboldened local conservationists, who have bucked the nation’s typically quiescent political culture and demanded greater openness in the public debate.
“In this globalized world, we are saying that governments and companies have to be accountable for the actions no matter where in the world they take place,” said Jacob Scherr, director of international programs at the Natural Resources Defense Council. “Globalization is a reality; you are seeing it in Belize. So we are using the tools of globalization to give concerned citizens a voice here and around the world.”
In turn, the council and other international groups have been vilified in the local press, called lawbreakers and terrorists (though no evidence is offered). A few leading citizens have called the environmental groups enemies of the nation that are trying to impose racist schemes to keep Belize undeveloped.
More restrained voices have said the environmental groups are denying this country the kinds of modern conveniences that others take for granted.
“We don’t think it is fair for these environmental groups to be beating up Belize over this little dam when their own countries have so many of them,” said Prime Minister Said Musa. “Now they are trying to tell us we can’t have one.”
The Chalillo Dam has been proposed since the early 1990’s. An initial feasibility study warned against it because of a potentially harmful environmental impact. More recent studies supported the project, though local environmental officials said those studies were inadequate.
Supporters of the project say it is necessary to resolve capacity problems with the country’s current dam and generator at Mollejón. The new dam at Chalillo, they said, would give them enough water to power the Mollejón generators through several months of the dry season.
In addition to the dam and generator at Mollejón, which was recently bought by Fortis Inc., the Canadian company that proposes building the new dam, Belize depends on pollution-prone diesel-powered generators for about a third of its power. Another third is supplied by a Mexican power grid.
“We need to find ways to remove our dependence on oil or Mexico,” said John Briceño, the deputy prime minister and minister of natural resources. “Yes, we get Mexican electricity sold to us at a subsidized rate, but even that is tied to the price of oil. And our agreement with Mexico ends in 2008, and what guarantees do we have that Mexico will give us the same agreement?”
But environmentalists say that in the near term, the cost of building a new dam would outweigh any possible savings in power generation. They add that Mexican power is still cheaper during off-peak hours, regardless of whether a new dam were built. They also accuse the government of overlooking alternative energy sources, like generators powered by burning waste.
One diplomat in Belize expressed doubt that the dam would bring down electric rates and said he suspected the project would enrich a few local business executives.